PHCC has begun work on repairing H piles over Bunn Lake at Highway 64 in Wake County, N.C.


Work involves dewatering work area, repairs to 40 14X73 piles with steel channels, cleaning, painting, and encapsulating supports with pile jackets. Work began on January 3 and is due to finish February 11.


Tom Barton is Project Manager and Luby Bell is Project Superintendent. The Owner is NCDOT.